WE are now five weeks into our Clubhouse Development and it's time for our latest update on the works.
We are looking to improve the Chinnor experience for players and spectators alike, with the works involving larger changing rooms, an extended balcony for spectators and socialising, and improved walk ways between the Clubhouse and Pitch 1 to help reduce the mud!
We can provide the following update after Week 5:
The blockwork has started, the cuts in the brickwork to form the new openings have been completed and both the electrician and fire alarm technician have been at work behind the scenes. The steelwork is due in the next couple of days...
A big thank you to everyone who has contributed so far and bought a brick. We are so close to hitting our fundraising target, and you can help us by clicking HERE.