WE are now eleven weeks into our Clubhouse Development and it's time for our latest update on the works.
We are looking to improve the Chinnor experience for players and spectators alike, with the works involving larger changing rooms, an extended balcony for spectators and socialising, and improved walk ways between the Clubhouse and Pitch 1 to help reduce the mud!
We can provide the following update after Week 11:
The new corridor access has been knocked through and with only one steel beam to fit, the space is looking good. Store cupboards and enclosures to the electrical switchgear are being formed. The supplier for the external stair has been appointed.
With only six weeks to completion, the race is now on to complete the internal alterations, finish the viewing terrace and repave parts of the external areas.
A big thank you to everyone who has contributed so far and bought a brick. We are so close to hitting our fundraising target, and you can help us by clicking HERE.