Clubhouse Development Update - Week 16

Clubhouse Development Update - Week 16

Alex Bond18 Aug 2016 - 15:49
Share via
FacebookTwitter
https://www.chinnor-rfc.com/ne

We're in the home straight now....

A quick update on what’s been going on this week with the development project at the club and the key events that everyone will need to be aware of in the coming week or so:

The lift is being installed on Monday which will allow the builders the begin the swap of the toilets. Therefore the upstairs toilets will be out of actions Monday, Tuesday and Wednesday of the w/c 22nd August. Downstairs toilets will still be available.

The shop is carpeted and the lights are fitted. The integral shutters need boxing in (and the shower ducting is still to be done). It is now ready for racking out. Practical items like the intruder alarm and fire alarm will be finalised and commissioned next week.

The paving out the front will be laid on Friday 19th and Saturday 20th August. This will finish of the outside of the building and give it that approachable look from the outside.

The glass has now been installed into the balustrade which is looking really nice and finishes off the entrance to the club.

We are aiming the snag the project on next week with hand-over then being either on Friday 26th August or just after the bank holiday week-end.